December 14, 2018 Update:

At the suggestion of the AWPCA, the Engineering Department installed 6 standpipes around the Project area to monitor groundwater levels in the Spring of 2018.  Since that time, Staff have been recording groundwater elevations to better ascertain potential impact due to groundwater during construction and seasonal expectations to minimize the impact.  The Department expects to continue the effort for 2019 and will be working on design strategies accordingly.  Residents are encouraged to check this Project page for updates.